Winter Special Flat 65% Limited Time Discount offer - Ends in 0d 00h 00m 00s - Coupon code: netdisc

Adobe AD0-E903 Adobe Workfront Project Manager Professional Exam Practice Test

Page: 1 / 7
Total 70 questions

Adobe Workfront Project Manager Professional Questions and Answers

Testing Engine

  • Product Type: Testing Engine
$43.75  $124.99

PDF Study Guide

  • Product Type: PDF Study Guide
$38.5  $109.99
Question 1

An organization has created unique data fields relevant to their projects. Starting by navigating from a project's landing page, where is this data found?

Options:

A.

Project Details > Custom Forms

B.

Project Details > Overview

C.

Business Case > Project Info

Question 2

The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed.

Which task settings should be configured to meet these requirements?

Options:

A.

The task Duration should be set to 2 days. A predecessor with a Finish-Start Dependency Type should be added to the second task with a lag of 5 days.

B.

Planned Hours should be set to 48 hours. A predecessor with a Finish-Start Dependency Type should be added to the first task with a lag of 5 days.

C.

The task Duration should be set to 48 hours. A predecessor with a Start-Finish Dependency Type should be added to the second task with a lag of 5 days.

Question 3

A project manager needs to locate the fixed revenue and costs of a project. Where should the project manager look to find this information?

Options:

A.

Business Case

B.

Billing Records

C.

Project Details

Question 4

A task owner has Time Off logged in Workfront for all of next week. The owner has a task that is planned to start and is due while she is out.

What action should the task owner take?

Options:

A.

Set the task condition to At Risk.

B.

Update the Commit Date on the task.

C.

Work on the task and complete it in the given duration.

Question 5

The art director is reviewing and approving a proof and has requested that they only get email notifications for a new proof or version. What Email alert option should be assigned to them on the workflow?

Options:

A.

Decisions and Notify recipients about this proof is selected

B.

Disabled and Notify recipients about this proof is selected

C.

Decisions and Notify recipients about this proof is not selected

D.

Disabled and Notify recipients about this proof is not selected

Question 6

Which date type on tasks can a project manager manually modify?

Options:

A.

Planned

B.

Estimated

C.

Projected

Question 7

Given this information regarding a Task:

    Planned Start Date: May 14

    Actual Start Date: May 14

    Planned Completion Date: May 20

    Projected Completion Date: May 22

    Percent Complete: 50%

    Duration: 5 Days

    Planned Hours: 8 Hours

    Status: In ProgressIf today's date were May 19, what would be the Task's progress status?

Options:

A.

Behind

B.

On Time

C.

At Risk

Question 8

A project manager wants to see all of the assignees for each task in a project.

Which field should the manager reference to view all task assignees?

Options:

A.

Assigned To

B.

Assignments

C.

Assigned

Question 9

An IT department needs to see the Group and Portfolio of each of its projects for reporting purposes.

In which project area does this information reside?

Options:

A.

Queue Details

B.

Project Details

C.

Metrics

Question 10

The last 5 tasks in a project need to happen within 10 days of the end of the project.

Which Task Constraint should the project manager use to configure this timeline without setting specific dates?

Options:

A.

Start No Later Than

B.

Must Start On

C.

As Late As Possible

Question 11

Which two options are available with Workfront reports? (Choose two.)

Options:

A.

A chart report that references a multi-select custom field

B.

Planned date-based calendar reports

C.

Filters with a custom grouping

D.

An object name with more than 500 characters

Question 12

Which date type should an assignee update to change the completion date of a task?

Options:

A.

Actual Completion Date

B.

Commit Date

C.

Planned Completion Date

D.

Projected Start Date

Question 13

A project manager has been asked to work on a cross-departmental company-wide initiative. There will be many individuals assigned to each task.

What should the project manager ask users to do when it comes to completing tasks?

Options:

A.

Users do not need to complete tasks when multiple users are assigned.

B.

Mark the task as "Done with my part."

C.

Make an update and tag the project manager.

Question 14

A client has negotiated a discounted billing rate for video editing in a specific initiative.

How can the project manager override the default billing rate for the Video Editor within a project?

Options:

A.

Temporarily change the billing rate for the Video Editor in the Workfront system, and then reset it once the client has been billed.

B.

Add a new billing rate to all tasks that involve video editing.

C.

Add a new billing rate within the project.

Question 15

What do the connector lines between tasks in a Gantt chart represent?

Options:

A.

Critical path

B.

Multiple assignments

C.

Predecessor relationship

Question 16

What occurs when an individual enters a new commit date that is after the original planned date of a task?

Options:

A.

The assignee of any task that has the original task set as a predecessor is notified.

B.

The Project Owner is notified whether this change will impact the Project Timeline.

C.

The Planned Completion Date of the task automatically changes to match the new Commit Date.

Question 17

An executive wants to see the actual cost of projects within a selected portfolio, allowing for multiple reports with the option to select a specific portfolio, sorted in a descending order, so the most expensive projects appear on top. Which steps should be taken to create this report?

Options:

A.

Visit the Reports area and create a new Project report. Add a column for Actual Cost and sort the column in descending order. From the Reporting Settings dropdown, add a prompt for Portfolio Name.

B.

Visit the Reports area and create a new Project report. Group the results by Portfolio Name. Add a column for Actual Cost and summarize this column by SUM.

C.

Visit the Reports area and create a new Project report. Add a column for Actual Cost and sort the column in descending order. Group the results by Portfolio Name.

Question 18

A project manager has set up and launched a new project for an annual marketing campaign.

Where can the project team locate their work requests?

Options:

A.

Email, Workfront Home, Project tasks list

B.

Email, Automatic Reminders, Workfront Home

C.

Event Notifications, Approval processes, Email

Question 19

Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.

What may have caused the planned start date of Task 2 to remain the same?

Options:

A.

The primary assignee had already submitted a Commit Date for the previous planned start date on Task 2, even though the project owner did not accept this Commit Date, the project plan made this date a Must Start On Constraint on Task 2.

B.

The project owner has at some point made a manual change to the planned start date of Task 2, which has in turn changed the Task Constraint of Task 2 to Must Start On.

C.

The primary assignee had scheduled time off during the new planned start date that Task 2 should have shifted toward. Due to this time off scheduled the date remained the same.

D.

The project owner has at some point made a manual change to the Task Constraint of Task 2 to As Soon As Possible, which has forced the date of Task 2 to be static.

Question 20

A company has decided that all projects for the year need to be created from templates and staffed in the following quarter. The projects will need to remain in a backlog until the team has capacity to work on them. There has been confusion previously because the team used Planning status for all work not started.

What should the project manager do to help the team see the difference between work in the backlog versus work that is now being planned?

Options:

A.

Load the project template once the team has bandwidth to start on the project.

B.

Create projects but leave the roles in place without assigning users.

C.

Create a custom status for Backlog to use prior to using the Planning status.

Question 21

A marketing team determines that in the future, their projects must be reviewed by the Project Sponsor before the project is closed. What is the best practice to ensure that each project is properly reviewed and approved?

Options:

A.

Create a new approval process in the global setup area that will ensure that an approval process is attached to all Marketing Projects.

B.

Create a single-use approval process on each project that routes to the Project Sponsor for approval once the project status is set to Complete.

C.

In the project template, add an approval process routing to the Project Sponsor for approval once the project status is set to Complete.

Page: 1 / 7
Total 70 questions