Winter Special Flat 65% Limited Time Discount offer - Ends in 0d 00h 00m 00s - Coupon code: netdisc

API API-580 Risk Based Inspection Professional Exam Practice Test

Page: 1 / 14
Total 140 questions

Risk Based Inspection Professional Questions and Answers

Testing Engine

  • Product Type: Testing Engine
$43.75  $124.99

PDF Study Guide

  • Product Type: PDF Study Guide
$38.5  $109.99
Question 1

The reduction in the ability of a component to provide its intended purpose of containment of Fluids

Options:

A.

Deterioration

B.

Damage

C.

Degradation

D.

Thinning

Question 2

Methods that use engineering judgment and experience as the bases for the analysis of probabilities and consequences of failure

Options:

A.

Quantitative risk analysis

B.

Qualitative risk analysis

C.

Process hazard analysis

Question 3

The primary work products of the rbi assessment and management approach and implementation of rbi provides

Options:

A.

Overall reduction of risk and acceptance of current risk

B.

Overall increase of risk and acceptance of risk

C.

Overall reduction of risk and negligence of current risk

D.

Overall increase of risk and negligence of current risk

Question 4

The event may be

Options:

A.

Singular or multiple

B.

Certain or uncertain

C.

Loss or gain

D.

Negative or positive

Question 5

Following is the unit of measure of consequence that is least developed among those currently used for rbi assessment

Options:

A.

Affected area

B.

Cost

C.

Environmental damage

D.

Safety

Question 6

Equipment reliability is especially important if leaks can be caused by

Options:

A.

Secondary failures, such as loss of utilities

B.

Primary failures such as leak due to severe corrosion

C.

Tertiary failures due to valve gland packing leak

Question 7

________________may result in the calculated corrosion rate appearingartificially high or low.

Options:

A.

Clerical error

B.

Measurement error

C.

Inspector error

D.

Ut scanning

Question 8

Reliability efforts, such as reliability centered maintenance (rcm), can be linked with rbi, resulting in an integrated program to

Options:

A.

Reducedowntime in an operating unit

B.

Reduce operating time of a unit

C.

To reduce risk by mitigation activities

Question 9

Rbi as an integrated management tool that complements.

Options:

Question 10

______________to be established to judge acceptability of risk couldhe an objective of the rbi assessment if such criteria do not exist already within the user's company.

Options:

A.

Risk criteria

B.

Risk plan

C.

Risk analysis

Question 11

The type of failure mode that likely to occur due to ssc

Options:

A.

Small holes to rupture

B.

Small holes

C.

Cracks

D.

Only rupture

Question 12

Deterioration susceptibility and rate can be done

Options:

A.

By groupingthe same material of construction/similar process/environment

B.

Not possible to group under any circumstances

C.

By random inspection method

Question 13

Qualitative assessment is done on the basis of

Options:

A.

Knowledge of operating History

B.

Inspection plans

C.

Possible material deteriorations

D.

All the above

Question 14

The risk assessment programme which focuses on process unit design andoperating practices and their adequacy given the unit's current or anticipatedoperating conditions

Options:

A.

Rbi

B.

Pha.

C.

Hazop

D.

Rcm

Question 15

Outcome of an event

Options:

A.

Consequence

B.

Risk

C.

Event

Question 16

Following are some of the recognized risks which cannot be managed by inspection alone except one

Options:

A.

Equipment nearing retirement

B.

Failure mechanisms (such as brittle fracture, fatigue) where avoidance of failure primarily depends on operating within a defined pressure/temperature envelope

C.

Consequence-dominated risks

D.

The suitability and current condition of the equipment within the current operating envelope will determine the probability of failure (pof) of the equipment from one or more deterioration mechanisms

Question 17

Process to find, list, and characterize elements of risk

Options:

A.

Risk estimation

B.

Risk evaluation

C.

Risk identification

Question 18

In most consequence evaluations, a key element in deter-mining the magnitude of the consequence is

Options:

A.

The volume of fluid released

B.

Amount of surface area exposed due to toxic release

C.

Physical area impacted by release

Question 19

The type of failure mode that likely to occur due thinning

Options:

A.

Larger leaks or rupture

B.

Only rupture

C.

Metal loss

D.

Cracks

Question 20

Reliability efforts, such as reliability centered maintenance (rem), can be linked with rbi, resulting in an integrated program to

Options:

A.

Reducedowntime in an operating unit

B.

Reduce operating time of a unit

C.

To reduce risk by mitigation activities

Question 21

The consequences of environmental damage are best understood by

Options:

A.

Cost

B.

Release

C.

Volume of fluid

D.

Toxic concentration

Page: 1 / 14
Total 140 questions