Control charts are used to do which of the following?
The implementation of a program designed to reduce changeover times will result in a temporary capacity shortage. This shortage will be handled by using some older equipment and by subcontracting some work. Which of the following methods should the company use to control capacity during this period?
Concurrent engineering is defined as which of the following approaches?
Which of the following concepts is a reason to create a visual factory?
A manufacturing facility is considering adopting cellular flow. Which of the following factors is most important to consider?
The best way to determine feasibility of the capacity plan for a work center is to use:
Which of the following steps should be first in determining operation start dates for capacity planning?
The actual output of a work center for a given time period can be determined by evaluating the:
Which of the following actions helps product design and development pursue a strategy of first-to-market?
Statistical process control is a technique primarily used to:
Which of the following persons has direct responsibility for the accuracy of production activity reporting?
Based on the data provided, assume that time available per day is 840 minutes. What is the takt time per unit of demand?
{exhibit 4027}
The primary reason for using an empty conveyance container as a triggering signal is to:
A customer has complained that paint is peeling off a product recently purchased from a supplier. A team is formed in the supplier plant to solve the problem and follow these steps:
{exhibit 534}
Which of the following methods best describes the problem-solving approach used by the team?
Structured problem solving provides what essential result to an organization?