Question 1

The pipes of a VESDA smoke detection system are installed at the air intake of the air conditioner inside the computer room.

Is this a good practice from an early smoke detection point of view?

Options:

A.

It depends on the type of gas-based fire suppression which will be installed.

B.

Yes, as this reduces the amount of piping to be installed in the data center, as all air will go through the air conditioner.

C.

No, the piping should be installed at the air exhaust of the air conditioner, as there can also be a fire inside the air conditioner itself.

D.

No, it will give a longer reaction time for the smoke detection system and there might also be bypass airflow.

Question 2

The humidity in the computer room has changed from about 50% down to 35% Relative Humidity (RH).

What influence does this have on Electrostatic Discharge (ESD)?

Options:

A.

No influence as long as the temperature is at approximately 20°C/77°F

B.

Relative humidity has no influence on ESD

C.

ESD levels will go up

D.

ESD levels will go down

Question 3

What is the main reason to install Earth Leakage protection?

Options:

A.

Protection of ICT equipment against high-frequency noise currents

B.

Protection of human lives

C.

Improvement of the data center grounding/earthing system

D.

Protection against lightning strikes

Question 4

You need to determine the strategy for the cooling audit. All the servers are based on a front-to-rear (F-R) airflow design.

Which location for the temperature/humidity measurement should you recommend for the audit?

Options:

A.

At the back/rear of the server at 50 mm/2 inch

B.

At 1.5 meters/5 feet above the floor in the middle of the cold aisle

C.

At the front/intake of the server at 50 mm/2 inch

D.

At 1.5 meters/5 feet above the floor in the middle of the hot aisle

Question 5

A data center has its own power supply from the public utility and receives chilled water supply from the building owner.

What needs to be taken into consideration when calculating the PUE?

Options:

A.

Nothing, as the chiller plant in the building also uses electrical power

B.

You will need to take the value for COP of the chiller plant into consideration

C.

You will need to take a weight factor of 0.4 for district chilled water into consideration

D.

PUE calculations are not possible in shared buildings

Question 6

What precaution shall be taken for cabling leading into an equipment rack when a data center is in a seismic-prone area?

Options:

A.

Cables should be loosely organized to allow for movement and be latched at the connectors.

B.

Cables shall be tightly organized to the rack and trays to avoid movement.

C.

Cables can be organized in any way as it is not important.

D.

Cables should be replaced by busbar trunking.

Question 7

What should be considered when installing overhead data cabling?

Options:

A.

To maintain minimum separation from power and ensure that the fire detection and suppression systems are not hindered.

B.

Copper data cabling should not be placed in metal cable trays.

C.

Optical fiber cabling should always be positioned on top of the copper cabling in the same cable tray to avoid damage to the sensitive optical fiber.

D.

All cabling should make sharp bends directly into the rack to avoid usage of additional space and blocking the airflow on top of the rack.

Question 8

When are the wet bulb and dry bulb temperatures identical?

Options:

A.

When the dry bulb's temperature is at the lowest allowable temperature for IT equipment as per ASHRAE

B.

When the dry bulb's temperature is at the highest allowable temperature for IT equipment as per ASHRAE

C.

When the relative humidity is at the best practice value for relative humidity, being 50% RH

D.

When the relative humidity is 100%

Question 9

What indicates the breaking capacity of a fuse or breaker?

Options:

A.

Mechanical strength of the casing of a fuse or breaker.

B.

The maximum voltage, in case of an electrical surge, that the fuse or breaker can handle without being destroyed or causing an electric damaging arc.

C.

The current at which the device will trip.

D.

The current that a fuse or breaker is able to interrupt without being destroyed or causing an electric damaging arc.

Question 10

From the options indicated, what is the correct starting point for the raised floor installation?

Options:

A.

Point A

B.

Point B

C.

Point C

D.

Point D

Question 11

Is it allowed to make design changes during the implementation phase?

Options:

A.

No, after a design freeze no further changes are allowed.

B.

Any change is fine as long as it is within the scope of the project.

C.

Yes, but only when time to implement is not exceeded.

D.

Only when there is a strong business and/or technical justification.

Question 12

You have three UPS systems connected in parallel. The UPS systems have an imbalance in the load sharing of approximately 20%.

What should you recommend?

Options:

A.

Review the cable lengths of each UPS to the common busbar

B.

Nothing, there is no reason for any concern

C.

Review the common mode noise levels within the computer room

D.

Review the harmonics levels within the computer room

Question 13

Smoke sensors need to be tested to ensure that they pick up a potential fire in the data center.

What should you recommend?

Options:

A.

Test the sensors by injecting smoke or simulated smoke directly into the sensor

B.

Press the self-test button on each sensor in the data center

C.

Inject smoke at the floor level

D.

Test the sensors according to the vendor specification

Question 14

The noise levels in the data center are approximately 91 dB (A).

Do employers need to take precautions?

Options:

A.

No, anything less than 100 dB (A) is acceptable.

B.

There are no regulations regarding noise levels inside a building. Regulations only apply to noise pollution outside of the building.

C.

As long as the data is compliant to ISO/IEC 27001 it is acceptable.

D.

Yes, since it is mandated by regulations.

Question 15

What is the main disadvantage of using a ToR (Top of Rack) design?

Options:

A.

A single ToR (Top of Rack) switch is more expensive than an EoR (End of Row) switch.

B.

You need a separate rack to install all your ToR (Top of Rack) switches.

C.

There will be more switches to manage.

D.

A ToR (Top of Rack) switch has only optical interfaces.

Question 16

Which formula is correct?

Options:

A.

Phase-to-Neutral Voltage = Phase-to-Phase voltage * 1.732

B.

Phase-to-Neutral Voltage = Phase-to-Phase voltage /1.732

C.

Phase-to-Neutral Voltage = Phase-to-Neutral voltage * 1.732

D.

Phase-to-Neutral Voltage = (Phase-to-Phase voltage * 1.732) / Phase-to-Neutral Voltage

Question 17

The logical overview of the data center looks as pictured. To what TIA-942 Rating is this design made based on electrical only?

Options:

A.

Rating - 4

B.

Rating - 3

C.

Rating - 2

D.

Rating - 1

Question 18

Three data centers are benchmarked on facilities energy efficiency.

Data center A has achieved a PUE of 2.45.

Data center B has achieved a PUE of 1.20.

Data center C has achieved a PUE of 1.90.

Which of the data centers is operating at the highest facility efficiency?

Options:

A.

PUE does not indicate efficiency

B.

Data center A

C.

Data center B

D.

Data center C

Page: 1 / 6