GAQM ISO-31000-CLA ISO 31000 - Certified Lead Risk Manager Exam Practice Test

ISO 31000 - Certified Lead Risk Manager Questions and Answers

Testing Engine

  • Product Type: Testing Engine
$37.5  $124.99

PDF Study Guide

  • Product Type: PDF Study Guide
$33  $109.99
Question 1

Due to the nature of crises, the management of a Crisis Management Team (CMT) usually requires which type of decision making structure?

Options:

A.

Centralized

B.

Networked

C.

Bottom-up

D.

Consensus-based

Question 2

What is typically the day-to-day responsibility of a Chief Risk Officer within a large organisation?

Options:

A.

Ensuring that all key risks are adequately managed and reported.

B.

Preparing and maintaining individual insurance arrangements

C.

Producing policies on compliance matters

D.

Providing assurance that individual risk management processes are effective.

Question 3

Which of the following is the current trend in auditing, risk management and compliance? 

Options:

A.

Providing assurance over threats

B.

Performing discrete audits in compliance with internal control

C.

Front office function providing leading indicators about risk

Question 4

Which element is often the biggest challenge in risk implementation?

Options:

A.

human

B.

computation

Question 5

Uncertainties may involve: (Choose two)

Options:

A.

The process used to conduct the risk analysis

B.

The processed to know upcoming security issues

C.

Differing abilities among risk analysts

D.

Appointing security analyst

Question 6

Risk management as defined by OCEG GRC model is:

Options:

A.

Capability to set and evaluate performance against objectives

B.

Capability to proactively identify, assess and address uncertainty and potential obstacles to achieving objectives

C.

Capability to proactively encourage and ensure compliance with established policies and boundaries

Question 7

Which of the following is an important aspect with stakeholders, customers, and interested parties is the essential element for maintaining the relevance of enhanced risk management within the structure of a changing context?

Options:

A.

Interviews

B.

Communication

C.

Brainstorming

D.

Session Storming

Question 8

Understanding the potential causes of risk events will primarily help an organisation to

Options:

A.

comply with corporate governance standards.

B.

eliminate all risks

C.

improve internal audit procedures.

D.

reduce the frequency of loss.

Question 9

Which risk identification involves creating alternative ways to achieve an objective?

Options:

A.

Scenario Based 

B.

Objectives-Based

Question 10

Which of the is a set of systematic, deliberate, and actionable steps to manage risk?

Options:

A.

Security

B.

Control

C.

Process

D.

Vision

Question 11

Which of the following consists of risk management principles, framework, and process that have been adopted as a national risk management standard by more than 60 countries?

Options:

A.

ISO 9001:2015

B.

ISO 27001:2013

C.

ISO 31000:2018

D.

ISO 14001:2018

Question 12

A systemic risk involves:

Options:

A.

A risk that loss in one area of an organization may cause loss in another area of the organization

B.

A risk that all of the current suppliers of an organization’s inputs will be unable to produce the inputs

C.

A risk that an event will cause multiple key people in an organization to leave at once

D.

A potential major disruption in the function of an entire market or financial system 

Question 13

Risk management is systematic, structured, and timely.

Options:

A.

True

B.

False

Question 14

The Chief Risk Officer within a large manufacturing organisation has been asked by the Board of Directors to provide an example of a pure risk. A suitable example would be

Options:

A.

a fire occurring in a new manufacturing process line.

B.

entering into a contract to purchase a new factory.

C.

making a strategic decision that affects the long-term future of the organisation.

D.

the purchase of a currency derivative.

Question 15

Which step is the risk process steps to manage, control, or remediate risk?

Options:

A.

Risk avoidance

B.

Risk identification

C.

Risk evaluation

D.

Risk treatment