New Year Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70special

SAP C_S4PPM_2021 SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management Exam Practice Test

SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management Questions and Answers

Testing Engine

  • Product Type: Testing Engine
$37.5  $124.99

PDF Study Guide

  • Product Type: PDF Study Guide
$33  $109.99
Question 1

You want to distribute capacity requirements in a project management project?

How can you distribute the values?

NOTE: There are 3 correct answers to this question

Options:

A.

Use a distribution function

B.

Copy values from resource assignments

C.

Apply a distribution rule

D.

Update the capacity requirements from the roll-up of task requirements

E.

Enter the vales manually

Question 2

What is the PR/PLAN_INI_PREP report used for?

Options:

A.

To create financial and capacity categories and groups based on customizing

B.

To upload financial data from Microsoft Excel

C.

To transfer costs from accounting objects to PPM

D.

To transfer recoded time from CATS to PPM

Question 3

Where can you define the scheduling type?

NOTE: There are 3 correct answers to this question.

Options:

A.

In customizing

B.

ON phase level

C.

On project definition level

D.

On task level

Question 4

In project management, what data can be copied from a project template during creation of a new project?

NOTE: There are 3 correct answers to this question.

Options:

A.

Authorizations

B.

Project structure

C.

Checklist

D.

Dates

E.

Responsible organizational unit

Question 5

Which of the project definition in project management must be filled before you can release a project?

Options:

A.

End date

B.

Responsible

C.

Project type

D.

Controlling area

Question 6

When is Bottom-up scheduling mandatory?

Options:

A.

When parallel phasing is used

B.

When actual time are recorded

C.

When constraints are used

D.

When summary tasks are used

Question 7

In project management, a WBS element for accounting integration was created automatically.

What is used to calculate the planned costs of this WBS element?

NOTE: There are 3 correct answers to this question

Options:

A.

Staffing of work in the role

B.

Duration planned on project tasks

C.

Demand planned on project roles

D.

Work planned on project task

Question 8

Resources are not shown in the Resource Overview

What is the reason for this?

NOTE: There are 2 correct answers to this question

Options:

A.

Assignment of resource management authorization object is missing

B.

Project response assignment

C.

Staffing manager assignment is missing

D.

Resource pool assignment is missing

Question 9

Which method can you use to update multiple values simultaneously in capacity planning for portfolio management?

Options:

A.

Distribution function

B.

Mass update

C.

Drag and drop

D.

XML upload

Question 10

Which of the following objects can you use to configure the cost integration from project system (PS) to SAP portfolio and project management (PPM)?

Options:

A.

Company code

B.

Controlling Area

C.

Cost Element

D.

Profit center

E.

CO Version

Question 11

Where can you create a status for a what-if scenario in portfolio management/

Options:

A.

In the what-if scenario classification

B.

In the review

C.

In the what-if scenario type

D.

In customizing for the portfolio type

Question 12

What are valid breakdown period for financial planning in portfolio management?

NOTE: There are 2 correct answers to this question.

Options:

A.

Years

B.

Days

C.

Weeks

D.

months