Question 1

Revenues & Payment

A customer use cross- company - code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal .. correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?

Options:

A.

Settle the WBS element to the highest billing element before you do the result analysis.

B.

Split the project intdifferent project according to each company code.

C.

Change the project structure so that it correspond better to the company's organization structure.

D.

Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly.

Question 2

Project structure.

You intent to work with predefined project coding mask to create project definitions. What do you have to consider?

Options:

A.

You can create project coding mask X... event if there are project numbers beginning with X.

B.

The standard project definition must differ from the definition of the operative project.

C.

You can use only numbers for a project coding mask definition.

D.

You can use an indicator to determine that only coded project numbers may be used within the project system.

Question 3

Project Structures

You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the

project.

What are the prerequisites?

Note: There are 3 correct answers to this question

Options:

A.

A bill of material with sales views

B.

A material master with sales views

C.

Assignment between material and standard network

D.

Standard network with activities

E.

A production order

Question 4

You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? Note: There are 3 correct answers to this question

Options:

A.

The formula for costing in the work center is incorrect

B.

The activity output price for the activity type and cost center assigned to the work center is not maintained.

C.

The duration is missing in the activity

D.

The Determine Costs indicator in the network header rules out planned cost calculation

E.

Integrated planning for the network is active

Question 5

Cost and budget

A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do

not want to produce..

Which setup do you recommend?

Options:

A.

Assign a sales order to a project with appropriate hierarchy levels.

B.

Assign a network to a sales order

C.

Assign Several production orders to a sales order

D.

Assign One production order to a sales order

Question 6

Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question

Options:

A.

Material master

B.

Network activity

C.

WBS element

D.

BOM item

Question 7

Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

Options:

A.

Individual overview capacity requirements

B.

Capacity load work center view

C.

Extended capacity evaluation

D.

Structure overview

Question 8

An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?

Options:

A.

The network profile

B.

The control key

C.

The table of MRP controllers

D.

The scheduling parameters for the network

Question 9

Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question

Options:

A.

In the project profile

B.

In the project version

C.

In the project type

D.

In the project definition of a standard WBS

E.

In the operative WBS element

Question 10

Dates

How are earliest dates and latest dates of activities schedule?

Options:

A.

Earliest dates are scheduled by backward scheduling, and the latest dates by forward scheduling.

B.

Earliest dates are scheduled by forward scheduling , and the latest dates by backward scheduling.

C.

Earliest dates and latest dates are scheduled by forward scheduling.

D.

Earliest dates are scheduled by backward scheduling, and the lates dates by copying the earliest dates.

Question 11

A customer needs to analyze the capacity requirements of their network activities. Which reports doyou recommend? Note: There are 2 correct answers to this question

Options:

A.

Resource reports

B.

Cost element reports

C.

Structure information system reports

D.

Hierarchical reports

Question 12

Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product.

What benefit do they have when using delivery from project (CNSO).

Options:

A.

With delivery from projects You can generate goods issues for project without creating delivery documents.

B.

With delivery from projects good receipt are automatically posted while saving.

C.

With delivery from projects you can generate purchase requisitions for sub-contractors.

D.

With the delivery from project you can deliver material component assigned to your network.

Question 13

The__________________that you specify when you create a project definition is unique for theentire project. Choose the correct answer.

Options:

A.

Plant

B.

Controlling area

C.

Company code

D.

Planning department

Question 14

What is the reason for assigning billing plans in customer projects?

Options:

A.

Billing plans are prerequisites for quotation creation

B.

Billing plans are used for revenue planning

C.

Billing plans are copied automatically to the sales order item.

D.

Billing plans enable the billing process to be carried out

Question 15

You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?

Options:

A.

Network profile

B.

Data entry profile

C.

Project profile

D.

Network type

Question 16

You want to establish costing for WBS. Costing should be easy to use and should not refer to cost elements. What method for costing do you use?

Options:

A.

Unit costing for WBS

B.

Easy Cost Planning (ECP) for WBS

C.

Detailed planning for WBS

D.

Planning of overall values