Question 1

What are some activities the project team will perform in executing project work during the Explore Phase?

Options:

A.

Deal with user authorization requests

B.

Collect project data and report on progress and performance

C.

Manage risks and implement risk response activities

D.

Establish and manage internal and external communications

E.

Manage Background Jobs, Input and Output

Question 2

In the "new implementation of SAP S/4HANA" transition path, which systems are part of the project system landscape?

There are 2 answers to this question.

Options:

A.

Starter system

B.

QAS

C.

P-system

D.

DEV

Question 3

What SAP middleware tool hosts the SAP Best Practices pre-delivered integration content and can be used for custom integration development?

Options:

A.

SAP HANA Enterprise Cloud

B.

SAP Cloud Platform

C.

Process Integration

D.

SAP API Management

Question 4

What can be found in the SAP Solution Implementation Roadmaps?

Options:

A.

Value Maps

B.

Deliverables in each Phase

C.

Accelerators to be used in the Project Library

D.

Detailed description of implementation tasks

Question 5

What are some core objectives of business process monitoring? 2 correct answers

Options:

A.

to provide transparency over end-to-end processes

B.

to provide process update and change feedback

C.

to provide reverse business process analysis

D.

to increase business process execution quality

Question 6

Custom Code Management process in SAP Solution Manager provides which of the following capabilities?

Options:

A.

Define KPIs and report on CCM data

B.

Retire unused/obsolete custom code objects

C.

Perform static code checks integrated into ABAP Development Tools on security, performance and syntax Replace custom developments with standard functions without necessity of a business process redesign

and dedicated project

D.

Identify custom code and collect its usage statistics

Question 7

Which activities are part of the Design and Configuration application of the SAP Activate methodology? There are 2 answers to this question

Options:

A.

Perform Fit/Gap Analysis

B.

Schedule kick-off workshop

C.

Confirm Integration prerequisites

D.

Conduct Scope Validation

Question 8

Which of the following is not about Fit/Gap Analysis (done during Explore Phase)? There are 2 answers to this question.

Options:

A.

Validate pre-activate and pre-assembled solution in the development system.

B.

Drive towards adopting customers processes.

C.

Minimize the needs for rework during realization.

D.

Prioritize delta requirement and gaps.

Question 9

Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning? Please choose the answer.

Options:

A.

Detailed bottom-up effort estimate the breaks each user story up into hours or shorter tasks

B.

Product Owner's relative estimate of the effort that will be needed to implement the user story

C.

Detailed bottom-up effort estimate by the SCRUM Master in story points based on the user story complexity

D.

Relative estimate in ideal person days that reflects the best estimate provided by the project team

Question 10

What structure level do you see when you access the Roadmap Viewer and chose work stream navigation? Please choose the correct answer.

Options:

A.

Task

B.

Deliverable

C.

Scenario

D.

Scope Item

Question 11

Which of the following is part of the Explore phase in the "New implementation od SAP S/4 HANA Cloud" transition path?

Options:

A.

Simplification and custom code impact analysis

B.

Setup and enablement

C.

Fit-to-standard

D.

Solution validation and Delta design

Question 12

Which activities are critical for delivering Agile projects? There are 2 answers to this question.

Options:

A.

Blueprint scheduling

B.

Release planning

C.

Sprint planning

D.

Retrospective agenda creation

Question 13

Which of the following belong to the application design and configuration workstream for SAP S/4HANA cloud in the explore phase?

There are 2 answers to this question.

Options:

A.

Fit-to-standard workshop

B.

Integration prerequisites confirmation

C.

Kick-off workshop

D.

Configuration definition

Question 14

What are some responsibilities of the Configuration Expert project team role in an SAP S/4HANA Cloud implementation?

Options:

A.

Resolution of business process issues

B.

Serves as the central contact for SAP

C.

Prepares and leads the Fit-to-Standard analysis process

D.

Manages interactions with the SAP Service Center

Question 15

What are some of the key characteristics of the impelemntation approach in the SAP Activate methodology? 2 correct answers

Options:

A.

Based on ready-to-use content

B.

Fixed scope

C.

Cloud ready

D.

On premise only

Question 16

What is the minimum number of quality gates mandated by the SAP Activate methodology?

Options:

A.

4

B.

0

C.

5

D.

3

Question 17

What can cloud-centric customers do with SAP Cloud ALM?

Options:

A.

Manage the Intelligent Enterprise

B.

Update cloud releases

C.

Configure their cloud products

D.

Track cloud services

Question 18

What are some of the benefits that apply to SAP Cloud ALM as a cloud product? Note: There are 2 answers to this question.

Options:

A.

The solution is always up to date.

B.

Different customer landscapes are all managed by SAP.

C.

User management is provided.

D.

The solution is always available.

Question 19

What is one of the main benefits of SAP Cloud ALM for operations that helps customers to improve efficiency?

Options:

A.

Workflow management

B.

Automation

C.

Integration optimization

D.

Business process improvements

Question 20

What are the three elements of SAP Activate? There are 3 correct answers to this question.

Options:

A.

Methodology

B.

Tools

C.

Focused Build Content

D.

SAP Solution Manager

E.

Content

Question 21

How can organizations closely connect subsidiaries with headquarters to run end-to-end business scenarios?

Options:

A.

With a fully functional ERP solution

B.

With a cloud solution

C.

With a 2-tier ERP solution

D.

With a 4-tier ERP solution

Question 22

Which of the following is true about the Customer Center of Expertise (CCoE)?

Options:

A.

CCoE centrally drive continuous improvement and continuous innovation.

B.

CCoE's mission is to provide transparency and efficiency of SAP implementation, innovation, operation, and quality of business processes and systems.

C.

CCoE is an organization model which serves as collaboration hub across IT and LoBs.

D.

CCoE is only involved during the hypercare period in supporting business processes operations.

Question 23

Which accelerators support the fit-to-standard workshop in the Explore phase? 2 correct answers

Options:

A.

test strategy

B.

Backlog template

C.

quality gate chaclist

D.

Business-driven configuration questionarie

Question 24

Where can you find Integration Content? 3 correct answers

Options:

A.

SAP Best Practice Explorer

B.

SAP API Business Hub

C.

Cloud Integration Automation service

D.

SAP Solution Manager

E.

SAP Cloud Appliance Library

Question 25

Which activity helps the project team to add the user stories to the product backlog? Please choose the answer.

Options:

A.

Planning the User Acceptance Test

B.

Conducting the Solution Validation

C.

Assessing Project Risks

D.

Preparing a Project Schedule