Question 1

True or False: Work Item Age is a leading indicator for the length of the Scrum Team's

feedback loop for that (in progress) item.

Options:

A.

True

B.

False

Question 2

Scrum Teams using Kanban can start to increase predictability by:

(choose the best answer)

Options:

A.

Visualizing the Workflow using a Kanban board.

B.

Improving transparency by having a CFD, Control Chart and Aging chart.

C.

Inspecting and adapting the Product Backlog during the Sprint Review.

D.

Reducing the amount of work in progress by introducing Work in Progress (WIP)

Limits.

Question 3

The Cycle Time metric for a certain Work Item cannot be used:

(choose the best two answers)

Options:

A.

As a leading indicator to the length of the feedback loop for that Work Item.

B.

To help the Scrum Team inspect and adapt their process.

C.

As a lagging indicator to the length of the feedback loop for that Work Item.

D.

To help the Developers inspect and adapt their Sprint in the Daily Scrum.

E.

To influence the team's SLE.

Question 4

Which of the following are lagging indicator metrics?

(choose the best three answers)

Options:

A.

Velocity.

B.

Cycle Time.

C.

Work in Progress.

D.

Throughput.

E.

Work Item Aging.

Question 5

Which of the following should NOT be in the Definition of Workflow?

(choose the best answer)

Options:

A.

Agreed owner of Workflow lane.

B.

Work in Progress (WIP) Limits.

C.

End of the Workflow.

D.

Start of the Workflow.

Question 6

How does Kanban for Scrum Teams maximize value delivered?

(choose the best two answers)

Options:

A.

By minimizing time spent in meetings/events.

B.

By enabling tighter empirical feedback loops via faster Cycle Times.

C.

By optimizing the flow of value.

D.

By minimizing transaction costs.

E.

By choosing higher-value items to deliver.

Question 7

What are possible benefits of supplementing Scrum with Kanban practices?

(choose the best four answers)

Options:

A.

May result in greater collaboration within the Scrum Team.

B.

Scrum Teams no longer need the Sprint time box.

C.

May reduce the average Cycle Time.

D.

Introduces better transparency into state of Work in

Progress (WIP).

E.

May help to discover areas of variability within your Sprint.

F.

Removes the need for the Sprint Planning event.

G.

Allows teams to release multiple times a Sprint.

Question 8

True or False: If Scrum is used with Kanban then having a Scrum Master is optional.

Options:

A.

True

B.

False

Question 9

Little's Law states that:

(choose the best answer)

Options:

A.

Average Cycle Time = Average Work in Progress / Average Throughput.

B.

Average Throughput = Average Cycle Time * Average Work in Progress.

C.

Average Work in Progress = Average Cycle Time / Average Throughput.

D.

Average Throughput = Average Cycle Time / Average Work in Progress.

Question 10

When using Kanban, it is useful to have explicit policies. What existing elements in the Scrum Guide might be used as explicit policies?

Options:

A.

Definition of Done.

B.

Definition of Ready.

C.

Product Backlog refinement.

D.

All of the above.

Question 11

What are the two things that constitute a Kanban board?

(Choose the best two answers)

Options:

A.

Swim lanes per Product Backlog item type.

B.

Visualization of your Workflow.

C.

Work in Progress (WIP) Limits.

D.

Class of service.

Question 12

What is a probabilistic forecast intended to communicate?

(choose the best answer)

Options:

A.

The best way to predict the future performance of a team.

B.

A guarantee of when a certain amount of scope will be complete.

C.

A forecast based on past performance that can help discussions about the likelihood

of achieving a certain goal in a given time frame.

Question 13

Which of the following are flow metrics needed when doing Scrum with Kanban?

(choose the best four answers)

Options:

A.

Throughput.

B.

Lead Time.

C.

Cycle Time.

D.

Work in Progress (WIP)

E.

Work Item Age

F.

CFD

Question 14

Upon which of the five Scrum Values does Professional Scrum with Kanban build?

(choose the best three answers)

Options:

A.

Courage.

B.

Transparency.

C.

Focus.

D.

Openness.

E.

Professionalism.

Question 15

For a specific Sprint Backlog item that has been started, what is the best chart (analytic) to

determine when it will be finished?

(choose the best answer)

Options:

A.

Throughput Run Chart.

B.

Cumulative Flow diagram (CFD).

C.

Work Item Aging Chart.

D.

Control chart.

Question 16

What are the four key flow metrics in Scrum with Kanban?

(choose the best answer)

Options:

A.

Work in Progress (WIP), Velocity, Lead Time, Cycle Time.

B.

Throughput, Work in Progress (WIP), Velocity, Lead Time.

C.

Velocity, Lead Time, Cycle Time, Cost.

D.

Work in Progress (WIP), Work Item Age, Throughput, Cycle Time.

Question 17

True or False: Limiting Work in Progress (WIP) will likely reduce the amount of collaboration in

the Scrum Team.

Options:

A.

True

B.

False

Question 18

Which of these is NOT a good description of Cycle Time?

(choose the best answer)

Options:

A.

The time a work item takes from initial idea/concept to feedback returned from

customers after a production release.

B.

The length of time a work item stays in one column.

C.

The number of items that move into the delivery/end point per time period (e.g.,

daily/weekly).

D.

The time a work item starts until when it finishes.

Question 19

A Service Level Expectation (SLE) forecast is a calculation about the future completion of an item that includes two things. What are those two things?

(Choose the best two answers)

Options:

A.

A commitment.

B.

A probability.

C.

A velocity.

D.

A range of elapsed days.

Question 20

What flow metric best indicates when multiple items from the Product Backlog will be finished?

Options:

A.

Throughput.

B.

Cycle Time.

C.

Work Item Age.

D.

Work in Progress (WIP).