As a Scrum Master how will you coordinate with the Product Owner to ensure Value-Driven Delivery on Scrum
projects?
To ensure that there is no gap between the customer's expectation from the project, and the deliverables
produced, the Scrum Master has to eliminate environmental obstructions that the team may face, that may
affect the quality of the deliverables. To do so, apart from Quality Planning, the team has to ensure Quality
Control, and Quality Assurance. Which of the following statements is true regarding Quality Assurance and
Quality Control?
Which of the following is the correct format for writing a User Story?
As a Scrum Master, you have to coordinate with the Product Owner to ensure that an appropriate Length of
Sprint is determined keeping in mind the changes expected. Which of the following statements is true in this
regard?
Which of the following statements about non-core Scrum roles is correct?
Which one of the following statements about the history of Scrum is NOT correct?
One week passes by, and less than half of the Product Backlog (requirements) is recorded. The Product Owner believes that it's best to start the first Sprint with this information, rather than waiting for the whole backlog to be completed. What should we do?
Which of the following statements about Release Planning Session is/are Correct?
A) Release Planning Sessions are conducted to develop a plan that defines when various sets of usable
functionality or products will be delivered to the customer.
B) Release Planning Sessions enable the Scrum Team to have an overview of the releases and delivery
schedule for the product they are developing.
C) Whether the releases will follow a phased deployment pattern or a continuous deployment pattern depends
on the stakeholder requirements.
D) Release Planning Sessions should produce a detailed Release Plan for the entire project.
One of the responsibilities of the Scrum Master is to ensure that the Product Owner does not change the
Acceptance Criteria of a committed User Story in the middle of a Sprint. In this regard, which of the following
statements about Acceptance Criteria is correct?
It is not allowed to change the members of the Development Team.
Change must be integrated properly in the Prioritized Product Backlog. In this regard, which of the following
statements is true?
You are the Scrum Master for a new project. This project will have 80 developers contributing to the product. As a Scrum Master, how would you divide a group of 80 people into multiple Development Teams?
Which one of the following INCORRECTLY matches a type of Scrum Team and a corresponding
communication facilitator?
A large software company has 8 Scrum teams with each team having a Scrum Master. After the Daily Standup
everyday with their respective teams, all Scrum Masters meet for a Scrum of Scrums. What are they likely to
do during this meeting?
Which of the following is true about Scrum?
Which of the following are important selection criteria while choosing a Scrum Master?
How long is a Sprint Retrospective in a one month Sprint?
Scrum Masters have to solve both internal and external impediments for the Scrum team during the Create
Deliverables process. To do so, they record the impediments in the Impediment Log during
_________________________.
A) Daily Standup Meetings.
B) Sprint Review Meetings.
C) Release Planning Meetings.
D) Sprint Planning Meetings.
Which of the following methods helps estimate the value provided by projects?
Which of the following is NOT an objective of a Retrospect Sprint Meeting?
You are the Scrum Master for a team that is working on a project for a chemical engineering company. During
one of the Sprints, the Product Owner suggests changes to the Acceptance Criteria on the basis of new
requirements by the stakeholders. Which of the following best describes the steps that should be taken next in
this situation?
All of the following events and activities are examples of adaptation, EXCEPT: