Question 1

What are the three phases within the Integrative Process Credit, Integrative Process?

Options:

A.

Pre-design, Discovery, Design and Construction

B.

Discovery, Design and Construction, Operations and Feedback

C.

Schematic Design, Design and Construction, Operations and Feedback

D.

Design Charrette, Schematic Design, Operations and Feedback

Question 2

In order for a product to contribute to Materials and Resources Credit, Building Product Disclosure and Optimization, Environmental Product Declarations, Option 1. Environmental Product Declaration, the product needs to be

Options:

A.

Forest Stewardship Council (FSC)-certified

B.

cradle-to-cradle certified

C.

third-party verified in a Corporate Sustainability Report (CSR)

D.

critically reviewed life-cycle assessment conforming to ISO 14044

Question 3

For Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan, which of the following

items is required for credit compliance?

Options:

A.

MERV 13 (F7) filtration media

B.

Indoor Environmental Quality test results

C.

Photographic documentation

D.

Separating construction waste

Question 4

Building Product Disclosure and Optimization is based on market

Options:

A.

reliability

B.

durability

C.

transparency

D.

consumption

Question 5

A project attempting to meet the preferred parking requirements for Location and Transportation Credit, Green Vehicles may provide what incentive to meet the requirements and highlight the project sustainable vehicle strategy?

Options:

A.

Three years of free parking for green vehicles

B.

Preferred parking decals for 5% of occupants utilizing carpool vehicles

C.

A permanent discounted parking rate of at least 20% for all green vehicles

D.

An annual maintenance voucher for at least 5% of occupants driving green vehicles

Question 6

For Location and Transportation Credit, Access to Quality Transit, a project team preparing timetables and service-level documentation must ensure the materials include

Options:

A.

verification that a weighted daily average has been used for each qualifying route

B.

confirmation that functional entries of the project are within 3/4 mi. (1.20 km) of the stop

C.

verification that a weighted building average has been used for each qualifying functional entry

D.

confirmation that each qualifying route features paired route service (service in opposite directions)

Question 7

A project's installed water fixtures do not exceed WaterSense maximum levels. Which compliance path should the LEED AP select under Water Efficiency Prerequisite, Indoor Water Use Reduction, and what type of documentation is required to demonstrate compliance with this path?

Options:

A.

Compliance Path 2: Usage-Based Calculation; prescriptive compliance confirmation

B.

Compliance Path 2: Usage-Based Calculation; appliance water calculations

C.

Compliance Path 1: Prescriptive Achievement; indoor water use calculations

D.

Compliance Path 1: Prescriptive Achievement; product cutsheets

Question 8

Which of the following is a biofuel that is considered renewable energy under Energy and Atmosphere Credit, Renewable Energy Production?

Options:

A.

Combustion of municipal solid waste

B.

Non-mill residue forestry biomass waste

C.

Wood coated with paints, plastics, or resins

D.

Animal waste

Question 9

Which group of chemicals emitted by some building materials is linked to asthma, chronic obstructive pulmonary disease, and cancer?

Options:

A.

Nitrogen Oxides (NOx)

B.

Polyvinyl Chlorides (PVCs)

C.

Chlorofluorocarbons (CFCs)

D.

Volatile Organic Compounds (VOCs)

Question 10

Which of the following will contribute to reducing the heat island effect?

Options:

A.

Artificial turf grass

B.

Intensive vegetated roof

C.

Steep sloped roof with initial SRI of 35

D.

Low sloped roof with initial Solar Reflectance Index (SRI) of 64

Question 11

What LEED Building Design and Construction project type should exclude weekend transit service from the transit service level calculations for Location and Transportation Credit, Access to Quality Transit, if the project occupants do not commute to the building during weekends?

Options:

A.

Schools

B.

Data centers

C.

Hospitality

D.

Warehouses and distribution centers

Question 12

The owner has stated a desire to provide a variety of non-automobile commuting options for the future occupants.

What credits should the LEED AP suggest to meet this goal?

Options:

A.

Sustainable Sites Credit, Heat Island Reduction and Location and Transportation Credit, Bicycle Facilities

B.

Location and Transportation Credit, Access to Quality Transit and Location and Transportation Credit, Sensitive Land Protection

C.

Location and Transportation Credit, Surrounding Density and Diverse Uses and Sustainable Sites Credit, Open Space

D.

Location and Transportation Credit, Reduced Parking Footprint and Location and Transportation Credit, Access to Quality Transit

Question 13

The contractor has submitted waste hauling reports for review in order to achieve Materials and Resources Credit, Construction and Demolition Waste Management. Which of the following materials on the documentation contribute towards the credit?

Options:

A.

Excavated soil

B.

Wood derived fuel

C.

Items sent to the local incinerator

D.

Alternate Daily Cover

Question 14

Which energy efficient lamp type is free from mercury?

Options:

A.

Compact Fluorescent

B.

High Pressure Sodium

C.

Light Emitting Diode

D.

T-8 Fluorescent

Question 15

Which is a benefit of earning Regional Priority credits?

Options:

A.

The LEED project can achieve more sustainable outcomes by recognizing the issues that are a priority in the project's location

B.

The context of the project's location is not addressed, allowing the project team to focus on the building's priority issues

C.

The project's operations are considered separately from design and construction, allowing the project team to focus on regional issues

D.

The LEED project is able to skip a review phase by considering the issues that are a priority in the project's location

Question 16

The project team wants to modify the design of an office building copy room to minimize the risk of airborne contamination to the surrounding space. The design includes a separate exhaust, but due to design constraints the partition walls of the room cannot run deck-to-deck. What can the team do to achieve Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies?

Options:

A.

Use MERV 8 (F5), or higher, filters

B.

Provide a hard-lid ceiling

C.

Create positive pressure in the room

D.

Provide a large opening to dilute air contaminates

Question 17

What is the average flush rate for a dual flush toilet with a high flush rate of 1.6 gpf (6 lpf) and a low flush rate of 1.05 gpf (4 lpf)?

Options:

A.

1.05 gpf (4 lpf)

B.

1.19 gpf (4.5 lpf)

C.

1.23 gpf (4.66 lpf)

D.

1.32 gpf (5 lpf)

Question 18

Which of the following is the location of CO2 sensors in naturally ventilated spaces to comply with the Indoor Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance?

Options:

A.

At least 6 ft. (2 m) above the floor

B.

At least 3 ft. (1 m) away from windows

C.

Between 3 ft. and 6 ft. (1 m and 2 m) above the floor

D.

On the ceiling 3 ft. (1 m) away from adjacent walls

Question 19

Which of the following prerequisites or credits are affected by using plug-in devices when attempting to achieve Indoor Environmental Quality Credit. Thermal Comfort?

Options:

A.

Energy and Atmosphere Credit. Demand Response

B.

Energy and Atmosphere Credit. Advanced Energy Metering

C.

Energy and Atmosphere Prerequisite. Minimum Energy Performance

D.

Energy and Atmosphere Prerequisite. Building Level Energy Metering

Question 20

What type of space must have self-closing doors, deck-to-deck partitions, and exhaust fans in order to meet the requirements for Indoor Environmental Quality Credit, Enhanced Air Quality Strategies?

Options:

A.

Data closet

B.

Conference room

C.

Chemical storage

D.

Open office

Question 21

The use of lead, mercury, copper and cadmium should be limited because they all

Options:

A.

are persistent bioaccumulative toxins

B.

reduce the life cycle assessment of a building

C.

take an unreasonable amount of energy to recycle

D.

interfere with the magnetic instruments in a medical building

Question 22

Which of the following assessments is conducted prior to the completion of the schematic design and explores methods to reduce energy use within a proposed building?

Options:

A.

Energy audit

B.

Building systems commissioning (Cx)

C.

Simple box energy analysis

D.

Mechanical systems inspection

Question 23

A project team is deciding on the impact of a proposed concrete walkway. Which of the following will be impacted as a result of adding the walkway?

Options:

A.

Site's impervious cover

B.

Project density calculations

C.

Erosion and sediment control plan during construction

D.

Air quality as a result of off gassing that occurs as concrete cures

Question 24

Green Infrastructure (GI) and Low-Impact Development (LID) rainwater management strategies improve upon the conventional approach for rainwater management by

Options:

A.

replicating a site's natural hydrology

B.

discharging rainwater at a faster rate

C.

increasing a site's impervious surface

D.

providing a greater volume of rainwater detention

Question 25

At the time of registering a project in LEED Online, Regional Priority credits are determined based upon the project's

Options:

A.

environmental zone

B.

longitude and latitude

C.

ASHRAE 90.1 - 2010 climate zone

D.

Environmental Protection Agency Phase I Assessment

Question 26

A project in a cold climate does not want a highly reflective roof because they want the heat absorption. How can this

project comply with Sustainable Sites Credit, Heat Island Reduction?

Options:

A.

The credit is not feasible for this project

B.

The credit may be achieved by using nonroof measures only

C.

The credit is applicable for projects that document this special condition

D.

The credit can only be achieved by using an alternative compliance path

Question 27

An owner has requested that the project team redesign a large office building. As part of the redesign, the owner would like to move the main entrance to the opposite side of the building. Achievement of which credit may be affected by the move?

Options:

A.

Location and Transportation Credit, High-Priority Site

B.

Location and Transportation Credit, Sensitive Land Protection

C.

Location and Transportation Credit, Surrounding Density and Diverse Uses

D.

Location and Transportation Credit, LEED for Neighborhood Development Location

Question 28

Which of the following methods is the referenced standard for demonstrating compliance with Indoor Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance?

Options:

A.

ASHRAE 62.2 - 2007

B.

ASHRAE 90.1 - 2010

C.

ASHRAE 55 - 2010

D.

ASHRAE 62.1 - 2010

Question 29

A topographic assessment of a project site located 150 ft. (45 m) from a water body was conducted. The results of the slope analysis show that the site is generally sloping 6% to 8% to the northwest over most of the site, with some steep slopes located at the eastern edge of the property, which may impact the runoff volume. Which one of the following LEED credits or prerequisites will be affected by these results?

Options:

A.

Sustainable Sites Credit, Rainwater Management

B.

Sustainable Sites Prerequisite, Environmental Site Assessment

C.

Location and Transportation Credit, Sensitive Land Protection

D.

Location and Transportation Credit, High-Priority Site

Question 30

The total land area within a 1/4 mi. (0.40 km) radius of a project boundary consists of 130 acres (53 hectares) and has a residential to nonresidential ratio of 60:40. Within this same total land area, there are 780 dwelling units and 1,600,000 ft2 (148 645 m2) of nonresidential building space. Given these parameters, what are the surrounding residential and nonresidential densities when attempting to achieve Location and Transportation Credit, Surrounding Density and Diverse Uses?

Options:

A.

10 dwelling units per acre (24 dwelling units per hectare) and a Floor Area Ratio (FAR) of 0.47

B.

10 dwelling units per acre (24 dwelling units per hectare) and a FAR of 0.70

C.

13 dwelling units per acre (32 dwelling units per hectare) and a FAR of 0.47

D.

15 dwelling units per acre (36 dwelling units per hectare) and a FAR of 0.70

Question 31

What is the reference standard that defines the requirements for LEED energy modeling?

Options:

A.

ASHRAE 62.1-2010

B.

Core Performance Guide

C.

ASHRAE Advanced Energy Design Guide

D.

ASHRAE 90.1-2010 Appendix G

Question 32

A project team wants to educate the facility manager on the installed building systems to improve Indoor Environmental Quality. They want the facility manager to maintain the systems so that they will continue to function as intended. Which of the following should be provided to the facility manager?

Options:

A.

Vendor invoices for mechanical equipment

B.

Preventive maintenance plan for the building

C.

As-built drawings and copies of material submittals

D.

A copy of the credit documentation for the credits that were approved by Green Business Certification Inc. (GBCI)

Question 33

A project team is attempting Location and Transportation Credit, High Priority Site, and selects Option 1: Historic District. To demonstrate that the project is in an infill site, the project team must confirm that:

Options:

A.

At least 75% of qualifying land areas within ¾ mile (1.20 km) are previously developed

B.

At least 75% of qualifying land areas within ½ mile (0.80 km) are previously developed

C.

The site is a brownfield as defined by the Environmental Protection Agency (EPA)

D.

The project is a Federal Renewal Community site

Question 34

The Required Breathing Zone Outdoor Airflow Vbz for a new banking facility is 0.120 CFM/ft2 (0.6 L/s/m2). If the team decides to attempt Increased Ventilation under Option 2 in the Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies, what is the minimum Design Zone Outdoor Airflow?

Options:

A.

0.144 CFM/ft2 (0.73 (L/s)/m2)

B.

0.156 CFM/ft2 (0.79 (L/s)/m2)

C.

0.168 CFM/ft2 (0.85 (L/s)/m2)

D.

0.30 CFM/ft2 (1.5 (L/s)/m2)

Question 35

A project team has installed a rainwater harvesting system on site. In which of the following could this system be recognized?

Options:

A.

Water Efficiency Credit, Water Metering and Water Efficiency Prerequisite, Indoor Water Use Reduction

B.

Water Efficiency Credit, Water Metering and Water Efficiency Prerequisite, Outdoor Water Use Reduction

C.

Sustainable Sites Credit, Rainwater Management and Water Efficiency Credit, Indoor Water Use Reduction

D.

Sustainable Sites Credit, Rainwater Management and Water Efficiency Prerequisite, Indoor Water Use Reduction

Question 36

Smoking is prohibited inside LEED-certified buildings in order to eliminate the health risks associated with environmental tobacco smoke. Which building type is exempt from this requirement?

Options:

A.

Office projects

B.

Healthcare projects

C.

Warehouse projects

D.

Residential projects

Question 37

When the LEED AP is applying the Integrative Process to a Building Design and Construction project, which of the following information is required to be present in the Owner's Project Requirements (OPR)?

Options:

A.

All applicable codes and standards

B.

Interior finishes related to the project

C.

All project team members and applicable roles

D.

Energy efficiency goals and training requirements

Question 38

During a design charrette, community neighbors raise a concern about potential glare resulting from a project's highly reflective roof. Which option should the LEED AP recommend to best address these concerns?

Options:

A.

Install a vegetative roofing system

B.

Change the design to reduce the amount of roofing area

C.

Change the roofing material to a dark material to eliminate the issue

D.

Increase the parapet height

Question 39

During construction, a value engineering exercise was conducted. This exercise has resulted in cost savings for the project. However, it is expected that the changes will affect some of the energy efficiency measures. The team has already submitted Energy and Atmosphere Credit, Optimize Energy Performance for review, and Green Business Certification Inc. (GBCI) returned an anticipated reply. What should the project team do in this situation?

Options:

A.

The project team should submit a clarification in the form of a narrative stating the changes in the design without updating the energy model

B.

At construction review submission, the energy model information must be updated to reflect all changes in the design, and the credit is guaranteed to be awarded

C.

The project team must incorporate the changes in their energy model and confirm the effect on the energy performance credit

D.

The project team need not do anything as GBCI already marked it as an "anticipated" credit

Question 40

Which rating system is being used if all of the credits below have been submitted towards certification?

- Location and Transportation Credit, Reduced Parking Footprint

- Energy and Atmosphere Credit, Fundamental Refrigerant Management

- Indoor Environmental Quality Credit, Acoustic Performance

- Materials and Resources Credit, Persistent, Bio accumulative, and Toxic (PBT) Source Reduction - Lead, Cadmium, and Copper

Options:

A.

Building Design and Construction: Schools

B.

Building Design and Construction: Healthcare

C.

Building Design and Construction: Hospitality

D.

Building Design and Construction: Data Centers

Question 41

A contractor is building a retirement community project. 30% of the building's product costs were derived from reused/salvaged materials or met recycled content criteria. Which of the following credits can the LEED AP submit towards certification?

Options:

A.

Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials

B.

Materials and Resources Prerequisite, Construction and Demolition - Waste Management Planning

C.

Materials and Resources Credit, Building Product Disclosure and Optimization - Material Ingredients

D.

Materials and Resources Credit, Building Product Disclosure and Optimization - Environmental Product Declarations

Question 42

In Sustainable Sites Credit, Light Pollution Reduction, which factor is included in the lamp lumen uplight calculation?

Options:

A.

Total fixture power

B.

Site area of the project

C.

Quantity of installed luminaires

D.

Total fixture lumens below 90 degrees

Question 43

Selecting a high-reflectance interior paint which is compliant with South Coast Air Quality Management District (SCAQMD) Rule 1113 can help contribute towards which two credits?

Options:

A.

Indoor Environmental Quality Credit, Low-Emitting Materials and Indoor Environmental Quality Credit, Interior Lighting

B.

Indoor Environmental Quality Credit, Low-Emitting Materials and Sustainable Sites Credit, Site Assessment

C.

Indoor Environmental Quality Credit, Low-Emitting Materials and Indoor Environmental Quality Credit, Minimum Indoor Environmental Quality Performance

D.

Indoor Environmental Quality Credit, Enhanced Indoor Environmental Quality Strategies and Indoor Environmental Quality Prerequisite, Minimum Indoor Environmental Quality Performance

Question 44

Which of the following project team members should be integrated early into the design phase to assist with earning the Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning?

Options:

A.

Owner

B.

Contractor

C.

Occupants

D.

Facility manager

Question 45

What percentage of all energy usage is attributable to buildings?

Options:

A.

60%

B.

30%

C.

40%

D.

50%

Question 46

Where must a building's no-smoking signage be posted?

Options:

A.

Within 10 ft. (3 m) of all building entrances

B.

Within 10 ft. (3 m) of the main building entrance(s)

C.

Within 25 ft. (8 m) of all building entrances

D.

Within 25 ft. (8 m) of the main building entrance(s)

Question 47

Which of the following is required for a cooling tower or evaporative condenser in Water Efficiency Prerequisite, Indoor Water Use Reduction?

Options:

A.

Alkalinity testing and ENERGY STAR® rating

B.

Non potable water sources and bacteria testing

C.

Water treatment calculations and system performance narrative

D.

Makeup water meters, conductivity controllers and overflow alarms

Question 48

How is the distance between the project site and the manufacturing location determined for Materials and Resources Credit. Building Disclosure and Optimization - Sourcing of Raw Materials. Option 2. Leadership Extraction Practices?

Options:

A.

Roadway distance

B.

Straight line distance

C.

Rail freight distance

D.

Air freight distance

Question 49

Which of these is a method to assess the regional context of a building's design for sustainability?

Options:

A.

Conducting a site analysis

B.

Consulting with neighbors

C.

Improving a design threshold

D.

Performing an energy analysis of the building

Question 50

Which of the following strategies can be used to reduce the internal load of a building?

Options:

A.

Decreasing lighting power

B.

Oversize the HVAC systems

C.

Install low reflective exterior facade

D.

Increase the insulating value of the glazing and window frame system

Question 51

To achieve the Sustainable Sites Credit, Light Pollution Reduction, Option 1. BUG Rating Method, projects must demonstrate

Options:

A.

all luminaires have full cutoff fixtures

B.

all luminaires have a minimum color temperature of 3500 K

C.

all luminaires meet acceptable fixture ratings for the project's Model Lighting Ordnance (MLO) lighting zone

D.

all luminaires are mounted at least three mounting heights from the lighting boundary

Question 52

Which system is eligible for the Energy and Atmosphere Credit, Renewable Energy Production?

Options:

A.

Ground-source heat pumps

B.

Tidal-based electrical production

C.

Municipal solid waste combustion

D.

Passive solar and daylighting strategies

Question 53

Which of the following cannot be classified as graywater?

Options:

A.

Water from toilets

B.

Water from showers

C.

Water from kitchen sinks

D.

Water from lavatory faucets

Question 54

A Healthcare Project is constructing a new building adjacent to an existing LEED Certified hospital facility. The new building's location is on the same hospital campus as the certified facility. The entire hospital campus was analyzed with an Environmental Site Assessment (ESA) as part of the certified facility's project scope. The new building project needs to complete a new Phase I ESA if

Options:

A.

the Phase II ESA uncovers suspected contamination

B.

contamination was identified by the certified facility

C.

the certified facility's Phase I ESA is older than 180 days

D.

the local equivalent standard is more stringent than ASTM E1527-05

Question 55

Which of the following projects is eligible to pursue the Energy and Atmosphere Prerequisite, Minimum Energy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide?

Options:

A.

50,000 ft2 (4 645 m2) office project

B.

80,000 ft2 (7 432 m2) hospital project

C.

110,000 ft2 (10 219 m2) school project

D.

140,000 ft2 (13 006 m2) retail project

Question 56

A new building containing private offices is pursuing Location and Transportation Credit, Access to Quality Transit. Which would comply?

Options:

A.

Locate the project ¼ mile (0.4 km) walking distance from two campus bus system lines (only accessible to campus students) with two stops each

B.

Locate the project ½ mile (0.8 km) walking distance from two bus lines with two stops each

C.

Locate the project ¼ mile (0.4 km) walking distance from a planned, funded, and partially complete subway station

D.

Locate the project ½ mile (0.8 km) walking distance from a planned, not funded commuter rail

Question 57

What standard should an engineer use when establishing minimum ventilation rates for a new mechanically ventilated space to earn Indoor Environmental Quality, Minimum Indoor Air Quality Performance?

Options:

A.

Local building code

B.

ASHRAE 62.1-2010

C.

International Mechanical Code 2012

D.

The ventilation code requiring the greatest volume of outside air

Question 58

How can a building owner promote both energy efficiency and thermal comfort in a building?

Options:

A.

Survey occupants about their comfort on a regular basis

B.

Provide occupants with individual space heaters in the winter

C.

Ask the cleaning contractor to turn off all of the lights after cleaning

D.

Institute a flexible dress code that permits seasonally appropriate clothing

Question 59

For a new project with a $10 million construction cost, the weight of the total recycled content is 0.9 tons (816.5 kilograms) each for post-consumer and pre-consumer recycled content. The value of the total recycled content is one million each for post-consumer and pre-consumer recycled content. What is the percentage of recycled content that contributes toward Materials and Resources Credit: Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2, Leadership Extraction Practices?

Options:

A.

33%

B.

20%

C.

40%

D.

18%

Question 60

A construction manager is looking for a project management tool that offers energy management strategies, benchmarking software tools for buildings, and product procurement guidelines. Which of the following is recognized by U.S. Green Building Council to assist them?

Options:

A.

Green Seal

B.

SCAQMD

C.

ENERGY STAR®

D.

SMACNA

Question 61

An office project has the following items in its break room kitchen: a kitchen sink, a residential-style dishwasher, and a coffee machine. How would these items be addressed in Water Efficiency Prerequisite, Indoor Water Use Reduction?

Options:

A.

The kitchen sink is included in fixture calculations, the dishwasher and coffee machine must be ENERGY STAR® or performance equivalent

B.

The kitchen sink is included in fixture calculations, the dishwasher must be ENERGY STAR® or performance equivalent, and the coffee machine is not included in the prerequisite

C.

The kitchen sink and dishwasher must be WaterSense labeled and the coffee machine is not included in the prerequisite

D.

The kitchen sink and dishwasher must be WaterSense labeled and the coffee machine should be included in fixture calculations

Question 62

Water Efficiency Prerequisite, Outdoor Water Use Reduction, Option 2. Reduced Irrigation, requires that a project's landscape water requirement be reduced by what percentage from the calculated baseline for the project site's peak watering month?

Options:

A.

20%

B.

25%

C.

30%

D.

40%

Question 63

A Photovoltaic (PV) system was installed on a 35,000 ft2 (3 252 m2) project. What actions need to take place in order to meet compliance for Energy and Atmosphere Prerequisite, Fundamental Commissioning (Cx) and Verification?

Options:

A.

No action is necessary as the PV system is not required to be commissioned

B.

The PV system installer should commission his own installations and share the results with the project owner

C.

The Cx agent for the project must conduct or oversee the Cx of the PV system

D.

The building's mechanical engineer should commission his own installations and share the results with the project owner

Question 64

A new Science Education Center is pursuing LEED certification. Which of the following strategies could be submitted to earn an Innovation in Design credit?

Options:

A.

The selection of energy-efficient LED fixtures for all of the building's lighting

B.

The installation of an air-purifying facade material on the front entrance of the building

C.

The integration of rainwater management strategies to achieve a Regional Priority Credit

D.

The implementation of a comprehensive metering strategy to measure three individual energy end uses

Question 65

Which of the following documents detail the ideas, concepts, and criteria determined to be important to the success of a building?

Options:

A.

Design review log

B.

Basis of design

C.

Integrated project delivery

D.

Owner's project requirements

Question 66

A LEED Building Design and Construction: New Construction office building's HVAC system includes hot water from a central utility plant. The central utility plant is owned and operated by a management company. The office pays a flat fee for hot water, included as part of the lease. The management company does not meter or invoice for actual hot water consumption. For the project to meet the requirements for Energy and Atmosphere Prerequisite, Building-Level

Energy Metering, an energy meter must be installed for

Options:

A.

natural gas

B.

hot water at the main service point

C.

nothing, because the flat fee is included as part of the lease

D.

nothing, because the energy source is outside of the project's scope

Question 67

A project team compares a life-cycle assessment (LCA) model to a baseline design to determine the reductions in six impact categories. One impact category exceeds the baseline by 7%. Which alternative analyses should the team run to check different impact measurements?

Options:

A.

Change the orientation of the design case building

B.

Optimize the slab depth of the design case building

C.

Decrease the gross floor area of the baseline building

D.

Increase the wall mass and types of windows in the baseline building

Question 68

What is the system boundary that a building life cycle analysis must be defined to account for?

Options:

A.

Cradle-to-gate

B.

Cradle-to-grave

C.

Cradle-to-cradle

D.

Cradle-to-building

Question 69

How much value would these two doors contribute toward Material and Resources Credit, Building Product Disclosure and Optimization – Sourcing of Raw Materials, Option 2. Leadership Extraction Practices?

Options:

A.

$150.00

B.

$50.00

C.

$100.00

D.

$125.00

Question 70

A downtown office building is unable to construct dedicated parking for its occupants. However, the building developer has partnered with a parking garage to offer discounted parking for its occupants. If the discounted parking rate is $450 per month, how much must the rate be for green vehicles for the building to receive one point for Location and Transportation Credit, Green Vehicles?

Options:

A.

$90

B.

$225

C.

$360

D.

$405

Question 71

Which of the following is an example of a nonroof measure for Sustainable Sites Credit, Heat Island Reduction?

Options:

A.

A playground with artificial turf

B.

A vegetated shading structure

C.

A shade structure with a three-year aged Solar Reflectance Index (SRI) value of 0.2

D.

A paving material with a three-year aged SRI value of 0.2

Question 72

Which of the following credit options can a project team attempt if a local, national, or international organization indicates that the neighborhood site of the project has a significant cultural value?

Options:

A.

Historic district

B.

Priority designation

C.

Brownfield remediation

D.

Diverse uses

Question 73

Which of the following pairs of strategies can help reduce the landscape water demand beyond the prerequisite level in Water Efficiency Credit, Outdoor Water Use Reduction?

Options:

A.

Mulched paths and weather sensor controls

B.

Artificial turf grass and alternative water sources

C.

Plant species selection and permeable pavement

D.

Alternative water sources and smart scheduling technology

Question 74

A project team is considering implementing a strategy that has previously been awarded as an Innovation credit on another project. Which actions should be followed if the project team wishes to gain formal pre-approval of the same strategy on the new project?

Options:

A.

Consult the LEED Administrator for the previous project

B.

Submit a Project Credit Interpretation Request (CIR) to GBCI

C.

Submit to Green Business Certification Inc. (GBCI) as-is

D.

The project is ineligible for an Innovation credit

Question 75

When the project occupancy is not known, which method is recommended?

Options:

A.

Default occupant density from ASHRAE 62.1-2010, Table 6-1

B.

Default occupant density from ASHRAE 90.1-2010, Table G3.1.1A

C.

Weekly average taken into account all the occupants in a typical 24-hour day of operation

D.

Occupancy measured for eight hours, between 8 a.m. and 5 p.m., for all occupancy patterns

Question 76

For a task chair purchased for a healthcare facility, which portion of the product contributes toward Materials and Resources Credit, Furniture and Medical Furnishings?

Options:

A.

Wheels, 4% of product by weight, that do not contain lead, mercury, cadmium or antimony

B.

Fabric, 5% of product by weight, with stain resistant treatment containing Perfluorinated Compounds (PFCs)

C.

Metal base, 20% of product by weight, which do not contain heavy metals and is not plated with hexavalent chromium

D.

Plastic armrests, 30% of product by weight, with added antimicrobial treatment

Question 77

The energy-related systems analysis for Integrative Process credit for Core and Shell projects should include all system loads and occupants required by which Energy and Atmosphere prerequisite?

Options:

A.

Building-level energy metering

B.

Fundamental commissioning and verification

C.

Minimum energy performance

D.

Fundamental refrigerant management

Question 78

A building owner in an arid climate is trying to design an outdoor lunch area for the tenants. Which landscaping strategy is important to employ in order to reduce water demand?

Options:

A.

Large maple trees for shading

B.

Xeriscaping landscape beds

C.

Turf grass area for picnic benches

D.

Tropical flowers next to park benches

Question 79

A design team is working on a hospital project. In order to meet the Energy and Atmosphere Prerequisite, Minimum

Energy Performance, what option is used?

Options:

A.

Whole building simulation

B.

EPA target finder rating tool

C.

Green-e Energy

D.

Advanced building core performance guide

Question 80

Which of the following Sustainable Sites credits are eligible to be used as a campus approach?

Options:

A.

Light Pollution Reduction, Places of Respite, Open Space

B.

Heat Island Reduction, Places of Respite, Site Master Plan

C.

Direct Exterior Access, Heat Island Reduction, Rainwater Management

D.

Heat Island Reduction, Light Pollution Reduction, Rainwater Management

Question 81

Sustainable Sites Credit, Site Assessment requires evaluation of

Options:

A.

soils, archeology, hydrology

B.

topography, hydrology, human use

C.

vegetation, topography, archaeology

D.

human health effects, climate, land value

Question 82

What is a viable strategy for optimizing open space under Sustainable Sites Credit, Open Space? U

Options:

A.

Coordinate open space features during the construction phase

B.

Minimize the floor-area ratio (FAR) and accessibility for open space

C.

Design a parking and road footprint layout that is not near open land

D.

Coordinate open space features early during the site planning phase

Question 83

A LEED AP submitted a Preliminary Design and Construction review and has received a review comment and technical advice on Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning. Which of the following actions should the LEED AP do if the project continues to pursue LEED certification?

Options:

A.

Revise the documentation and resubmit the form

B.

Abandon meeting this prerequisite

C.

Submit an appeal to Green Business Certification Inc.

D.

Ask the General Contractor to be more aggressive with recycling goals

Question 84

Which of the following are all considered regular building occupants?

Options:

A.

Staff, primary/secondary students, volunteers, and residents

B.

Staff, primary/secondary students, higher education students, and residents

C.

Higher education students, retail customers, periodic volunteers, and visitors

D.

Residents, volunteers, retail customers, and staff

Question 85

A project team member has prepared a map and accompanying table as documentation for the Location and Transportation Credit. Surrounding Density and Diverse Uses. Option 2. Diverse Uses. The map includes the location of each diverse use. the location of the project and the main entrance of the building. The table includes the distance to each use. the name of each use and the category of each use The team lead reviews the documentation and notes an important missing item. Which of the following is the most important item to add to the documentation?

Options:

A.

A description of each use

B.

The location of parking lots near each use

C.

Walking routes from the project to each use

D.

A calculation of the expected number of project occupants who will visit each use

Question 86

A project team is providing additional ventilation under Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies. What credit could this adversely affect?

Options:

A.

Energy and Enhanced Commissioning

B.

Indoor Environmental Quality, Thermal Comfort

C.

Energy and Atmosphere, Optimize Energy Performance

D.

Indoor Environmental Quality, Interior Lighting

Question 87

A new five-story building with a 30,000 ft2 (2 800 m2) footprint is being designed on a previously disturbed100,000 ft2 (9 290 m2) site. The remaining on-grade surface will be 35,000 ft2 (3 250 m2) of asphalt parking, and 35,000 ft2 (3 250 m2) of native vegetated open space. To achieve a point for exemplary performance under Option 1 of Sustainable Sites Credit, Site Development - Protect or Restore Habitat, the design team will have to incorporate a native and/or adapted vegetated roof with a minimum area of

Options:

A.

12,500 ft2 (1 160 m2)

B.

15,000 ft2 (1 400 m2)

C.

25,000 ft2 (2 300 m2)

D.

35,000 ft2 (3 250 m2)

Question 88

Several Materials and Resources credits give a bonus location valuation factor, which allows products extracted,

manufactured and produced within 100 mi. (161 km) of the project to take double valuation in credit calculations. The

intent of this bonus is

Options:

A.

to shorten construction duration by reducing shipping times

B.

to avoid spreading products with potentially invasive non-native pests

C.

to incentivize the purchase of products that support the local economy

D.

to promote design with indigenous materials in order to maintain local aesthetic quality

Question 89

A tenant of a new office building will require 100 workstations per floor. Each floor will have two bathroom facilities and one conference room. How many lighting control devices with at least three lighting levels per floor are required to comply with Indoor Environmental Quality Credit, Interior Lighting, Option 1. Lighting Control?

Options:

A.

91 lighting control devices

B.

93 lighting control devices

C.

100 lighting control devices

D.

103 lighting control devices

Question 90

A project is designed to remodel an existing warehouse into multi-family housing. The exterior facade of the warehouse will remain, but 40% of the interior will be demolished and replaced for interior new construction. New materials will be used for the new construction. To achieve points in the Materials and Resources Credit, Building Life-Cycle Impact Reduction, which credit path option would apply?

Options:

A.

Historic Building Reuse

B.

Building and Material Reuse

C.

Whole-Building Life-Cycle Assessment

D.

Renovation of Abandoned or Blighted Building

Question 91

A project team is attempting Location and Transportation Credit: High Priority Site and selects Option 1: Historic District. To demonstrate that the project is located in an infill site, the project team must confirm that:

Options:

A.

At least 75% of qualifying land areas within 3/4 mile (1.20 km) are previously developed

B.

At least 75% of qualifying land areas within 1/2 mile (0.80 km) are previously developed

C.

The project is a Federal Renewal Community site

D.

The site is a brownfield as defined by the Environmental Protection Agency

Question 92

When the LEED AP is applying the Integrative Process to a Building Design and Construction project, which of the following must be included in the Basis of Design (BOD)?

Options:

A.

Training requirements

B.

Allowable tolerance for facility operations

C.

Facility, system and assembly performance assumptions

D.

Environmental, energy efficiency and sustainability goals

Question 93

To achieve the Sustainable Sites Credit, Light Pollution Reduction, Option 1. BUG Rating Method, projects must demonstrate:

Options:

A.

All luminaires have full cutoff fixtures

B.

All luminaires are mounted at least three mounting heights from the lighting boundary

C.

All luminaires have a minimum color temperature of 3500 K

D.

All luminaires meet acceptable fixture ratings for the project’s Model Lighting Ordinance (MLO) lighting zone

Question 94

Which of the following projects are eligible for LEED certification?

Options:

A.

Prefabricated sandwich panel house

B.

New office building 900 ft² (83.6 m²)

C.

Houseboat

D.

Mobile home

Question 95

A building owner installs a building automation system (BAS) to allow programmable load control. Which of the

following credits can be pursued because of the installation?

Options:

A.

Energy and Atmosphere Credit, Demand Response

B Energy and Atmosphere Credit, Ongoing Commissioning

B.

Energy and Atmosphere Credit, Enhanced Commissioning

C.

Energy and Atmosphere Credit, Enhanced Refrigerant Management

Question 96

Which of the following will result in a higher demand for potable water use in irrigation?

Options:

A.

Sparsely planted area

B.

Drip irrigation system

C.

High evapotranspiration rate

D.

Rainwater harvesting system

Question 97

A LEED Building Design and Construction project includes an outdoor stage for theatrical performances. In pursuit of Sustainable Sites Credit, Light Pollution Reduction the engineer has specified an LED fixture to illuminate actors on the stage while limiting light pollution. Which of the following suggestions should the LEED AP give to the project owner?

Options:

A.

Modify the design to enclose the performance areas

B.

Calculate the return on investment over the 20-year life of the project

C.

Compare the energy consumption against an alternative

D.

Inform the owner that the LED fixture is exempt from Sustainable Sites Credit, Light Pollution Reduction

Question 98

Which individual occupant lighting control meets the requirements of Indoor Environmental Quality Credit, Interior Lighting?

Options:

A.

Two Level (on, off)

B.

Three Level (on, 25%, off)

C.

Three Level (on, 50%, off)

D.

Three Level (on, 75%, off)

Question 99

Which of the following credit categories identifies environmental issues that are most relevant for a project's chapter area or country?

Options:

A.

Location and Transportation

B.

Energy and Atmosphere

C.

Sustainable Sites

D.

Regional Priority

Question 100

Which of the following documents contains the design team's interpretation of the Owner's Project Requirements?

Options:

A.

Basis of Design (BOD)

B.

Simple Box Energy Model Analysis

C.

System's manual

D.

Integrated Project Delivery report

Question 101

During preliminary energy analysis, what energy reduction strategies can best help in reducing the energy load in the new building construction project?

Options:

A.

Green roof

B.

Site conditions

C.

Massing and orientation

D.

Programmatic and operational parameters